Outline of Total Water Management Plan
1. Test fresh incoming water for 15 specific items
a. To determine quality and problems of incoming water
b. To offer options for treating problems
c. Establish incoming water management plan
2. Wastewater testing of 26 specific items
a. to determine ability to meet discharge regulations
b. to offer options for treating for reuse/reclaim
c. to establish wastewater management plan
3. Interpret the report by identifying which test results are within acceptable ranges
and identifying those which are outside the acceptable range.
a. Explain the consequences of operating outside the acceptable range.
b. Provide solutions for bringing them into acceptable range.
4. Provide written outline, detailed processes and list of equipment recommended
including cost range and payback periods to treat incoming water as called for
from the 15 specific items tested plus pressure and flow requirements, odor
control and silt and any other potential problem areas that have been discovered.
5. Provide written plan, detailed processes and list of equipment recommended with
cost range and payback periods for treating wastewater as required for the 26
specific items, plus odor control, and any other potential problem areas that have
been discovered.
|